{meta} Decision - Trafford Road Improvements – Statutory Undertakers C6 Issue of Main Orders under the New Roads and Streetworks Act 1991

Decision details

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: Yes

Decision:

Salford City Council - Record of Decision

 

I Paul Dennett, City Mayor, in exercise of the powers contained within the Council Constitution do hereby approve:

The creation of the following multiple purchase orders totalling £1,475,864.00 to enable C6 payments under NRSWA to be made for Trafford Road Enabling Works – Statutory Undertakers Diversions and Drainage Investigations to be carried out between 20-01-20 and 22-06-20:

 

Statutory Diversion Costs

 

 

BT*

£

166,966.49*

BT Payphones

£

14,563.00

City Fibre

£

43,719.91

Colt

£

238,163.17

Electricity North West

£

118,299.36

Instalcom

£

18,397.13

Cadent Gas

£

33,443.93

SSE

£

40,745.39

Virgin Media

£

1,322.95

Vodafone*

£

179,557.00*

Contingency for C3 / C4 fluctuation

£

620,685.67

 

£

1,475,864.00

 

 

The Reasons are; In order to reduce the risk on the main works package the diversionary works are to be undertaken upfront which in turn will reduce the main programme timescales and benefit the construction phase of the project.

Options considered and rejected were – The proposed highway alignment has been tweaked and revised numerous times to reduce as far as practically possible the requirement for diversions however some diversionary works cannot be avoided.

Assessment of Risk – Low

 

Approval of decision will allow PO’s to be raised to start the Statutory Undertakers mobilisation which would otherwise delay the commencement of these works and push back the main works package. It is noted that C5/C6 Purchase Orders can be cancelled prior to works commencing and will be kept under review pending FBC submission and approvals.

The source of funding is TfGM Growth Deal 3 Fund

 

Legal Advice obtained - Yes

Financial Advice obtained – Yes

Procurement Advice obtained - Yes

The following documents have been used to assist the decision process. The relevant documents contain exempt or confidential information and are not available for public inspection:

Report to Property & Regeneration on 10th July 2019.

 

Contact Officer: Ryan Adamson                        Tel No 0161 779 6158

 

*         This decision is not subject to consideration by another Lead Member         

 

*         The appropriate scrutiny committee to call-in the decision is the Growth and Prosperity Scrutiny Panel.

 

 

 

Signed:       PAUL DENNETT                 Dated:      27 November 2019                                                          

                     City Mayor  

 

 

FOR DEMOCRATIC SERVICES USE ONLY

 

*         This decision was published on 27 November 2019                                            

 

*         This decision will come in force at 4.00 p.m. on 4 December 2019                                 unless it is called-in in accordance with the Decision Making Process Rules.

 

Publication date: 27/11/2019

Date of decision: 27/11/2019

Decided at meeting: 27/11/2019 - Procurement Board