{meta} Agenda for Procurement Board on Tuesday, 14 December 2021, 12.00 pm

Agenda and decisions

Venue: Salford Suite, Salford Civic Centre, Chorley Road, Swinton. View directions

Contact: Carol Eddleston, Senior Democratic Services Advisor 

Items
No. Item

1.

Apologies for absence

2.

Declarations of interest

3.

To approve, as a correct record, the minutes of the meeting held on 8th December 2021 pdf icon PDF 422 KB

4.

Matters arising

5.

Decision items - Part 1 (open to the public)

5a

Request for Approval - Contract Award - Technical Services and Highway Works Framework - Hayley Nixon / Charlotte Pritchard pdf icon PDF 597 KB

Decision:

Salford City Council - Record of Decision

 

I, Councillor Hinds, Lead Member for Finance and Support Services and Chairman of the Procurement Board, in exercise of the powers contained within the Council Constitution do hereby approve the Technical and Highway Works Framework as outlined in the table below.

 

Detail required

Answers

Title/Description of Contracted Service/Supply/Project

Technical and Highway Works Framework

Name of Successful Contractor

Name of Contractor

 

Type of Organisation

Registration No

SME/Non SME

Lot 1

- Argyle NW

Construction Ltd

 

- Colas Limited

 

- Rosgal Limited

 

- P Casey (Land Reclamation) Ltd

- Bethell Construction Limited

- Eric Wright Civil Engineering Ltd

 

- Limited Company

 

 

- Limited Company

 

- Limited Company

 

- Limited Company

 

- Limited Company

 

- Limited Company

 

 

- 02829893

 

 

- 2644726

 

- 3731189

 

- 1122137

 

- 0264322

 

- 2565379

 

 

 

- SME

 

 

- Non SME

- SME

 

- Non SME

- SME

 

 

- SME

 

Lot 2

- Coating Services

Ltd

- Protek Fencing Ltd

 

 

- Limited Company

 

- Limited Company

 

- 3852483

 

- 2197089

 

 

- SME

 

- SME

Lot 3

- Colas Limited

 

- Rosgal Limited

 

- General Utilities

Northwest Ltd

- AE Yates Ltd

 

- Bethell Construction Limited

- No Dig Drainage

Solutions Ltd

 

 

- Limited Company

 

- Limited Company

 

- Limited Company

 

- Limited Company

 

- Limited Company

 

- Limited Company

 

- 2644726

 

- 3731189

 

- 6468779

 

- 415632

 

- 0264322

 

- 10378682

 

- Non SME

 

- SME

 

 

- SME

 

 

- SME

 

- SME

 

 

- SME

Lot 4

- P Casey (Land Reclamation) Ltd

- Eric Wright Civil Engineering Ltd

- Coating Services

Limited

-Amalgamated

Construction Ltd

(trading as

AmcoGiffen)

- AE Yates Ltd

- Bethell Construction

 Ltd

 

- Limited Company

 

- Limited Company

 

- Limited Company

 

- Limited Company

 

 

 

- Limited Company

- Limited Company

 

 

- 1122137

 

-  2565379

 

- 3852483

 

- 995892

 

 

 

-  415632

-  0264322

 

- Non SME

- SME

 

- SME

 

- Non SME

 

 

- SME

 

- SME

 

Lot 5

- Pavement Testing

Services Ltd

- Construction Testing Solutions Limited

- Concept Engineering Consultants Ltd

 

- Limited Company

 

- Limited Company

 

 

- Limited Company

 

 

- 04374737

 

- 05998333

 

 

- 03401367 

 

- SME

 

 

- Non SME

 

 

 

- SME

Lot 6

- P Casey (Land Reclamation) Ltd

- Wright Landscapes

 Ltd

- Horticon Ltd

- Groundwork

 Landscape Ltd

- Landscape

Engineering Ltd

- Bethell Construction

Ltd

 

- Limited Company

 

- Limited Company

 

- Limited Company

- Limited Company

 

- Limited Company

 

- Limited Company

 

 

- 1122137

 

- 04611247

 

- 2463376

- 1339901

 

- 04049863

 

- 0264322

 

- Non SME

- SME

 

- SME  

 

- SME

 

 

 

- SME

Framework Value (£)

£          40,000,000 full project

Contract Duration

3 years (+1)

Contract Start Date

03/01/2022

Contract End Date

03/01/2025

Optional Extension Period 1

12 months

Optional Extension Period 2

N/a

Who will approve each Extension Period?

Procurement Board (extension > £150k)

Contact Officer (Name & number)

Shoaib Mohammad

Lead Service Group

Place

How the contract was procured?

(to be supplied by procurement)

Open Tender

Framework Details (where applicable)

(procurement body, framework reference  ...  view the full decision text for item 5a

5b

Request for Approval - Contract Award - Chapel Street East Phase 1 - Simon Telford pdf icon PDF 582 KB

Additional documents:

Decision:

Salford City Council - Record of Decision

 

I, Councillor Hinds, Lead Member for Finance and Support Services and Chairman of the Procurement Board, in exercise of the powers contained within the Council Constitution do hereby approve the award of the contract as outlined below:

 

Detail required

Answers

Title/Description of Contracted Service/Supply/Project

Chapel Street East Phase 1

Name of Successful Contractor

The Casey Group Limited

Supplier Registration Number

(to be supplied by Corporate Procurement)

04233269

Type of organisation

(to be supplied by Corporate Procurement)

Private Limited Company

Status of Organisation

(to be supplied by Corporate Procurement)

SME

Contract Value (£)

£2,365,431.37

Full project

Risk Allowance

£429,937.34

Risk Allowance

Contract Duration

10 months

Contract Start Date

14/02/2022

Contract End Date

09/12/2022

Optional Extension Period 1

Not applicable

Optional Extension Period 2

Not applicable

Who will approve each Extension Period?

Procurement Board (extension > £150k)

Contact Officer (Name & number)

Simon Telford, 07799677214

Lead Service Group

Place

How the contract was procured?

(to be supplied by procurement)

Mini Competition

Framework Details (where applicable)

(procurement body, framework reference & title, start/ end date

Bolton Council Highways Framework Contract – Lot 3 (NEC4 Option B – Priced Contract with Bill of Quantities)

Funding Source

Grant Funding from Mayors Challenge Fund &

Local contribution – S106 and Developer Contribution

Ethical Contractor (EC): Mayor’s Employment Charter

 

 

EC: Committed to sign up to charter

EC: Accredited Living Wage Employer

Wishes to seek accreditation


 

The Reasons are

 

  1. Chapel Street East Phase 1 gained programme entry to Tranche 1 of the Mayors Challenge Fund (MCF) in July 2018. To date approval has been granted for the advanced drawdown of £397,936.85 to fund scheme development up to business case submission.  

 

  1. The majority of the scheme’s funding for the delivery phase is to come from the Mayor’s Challenge Fund. A business case for the scheme is to be submitted to Transport for Greater Manchester in December 2021 to award funding for the delivery of the scheme. The outcome of the assessment of the business case and approval for funding is expected January 2021.

 

3.    Local contributions have been identified from within the City Council’s S106 receipts and through contributions agreed with third parties. S106 funds for the scheme totalling £305,720 have been received and approval has been granted for their allocation to the Chapel Street East Phase 1. Agreement in principle has been received from Salford City Council’s Development Partner English Cities Fund for a contribution of £190,000.

 

4.    A compliant mini-competition has taken place, using an existing framework, to select a preferred Principal Contractor.

 

  1. If approved, the scheme is proposed to commence 14th February 2021.

 

 

Options considered and rejected were

The procurement route selected for Chapel Street East Phase 1 was the City Council’s existing Bolton Council Highways Framework Contract – Lot 3 (NEC4 Option B – Priced Contract with Bill of Quantities).

All five tenderers on the framework were invited to tender in the form of a mini-competition. There were three returned tenders, all of which  ...  view the full decision text for item 5b

6.

Any other urgent business - Part 1 (open to the public)

6a

Approval to Award the Contract related to MyWork Campus Digital Infrastructure Upgrade. This is for Supply, Installation and Maintenance of Lot 3 – [MY] Booking Application - Steven Fry/Matt Wall pdf icon PDF 201 KB

Additional documents:

Decision:

Salford City Council - Record of Decision

 

I Councillor Hinds, Lead Member for Finance and Support Services and chairman of the Procurement Board, in exercise of the powers contained within the Council Constitution do hereby approve:

 

Approval to Award the Contract related to MyWork Campus Digital Infrastructure Upgrade. This is for Supply, Installation and Maintenance of Lot 3 – [MY] Booking Application as outlined below:

Detail required

Answers

Title/Description of Contracted Service/Supply/Project

Lot 3 – [MY] Booking Application

Name of Successful Contractor

CDW

Supplier Registration Number

(to be supplied by Corporate Procurement)

02465350

Type of organisation

(to be supplied by Corporate Procurement)

Private Limited Company

Status of Organisation

(to be supplied by Corporate Procurement)

Non-SME

Contract Value

£365,960.45

Full Project

Contract Duration

60 months

Contract Start Date

01/01/2022

Contract End Date

01/01/2027

Optional Extension Period 1

N/A

Optional Extension Period 2

N/A

Who will approve each Extension Period?

Procurement Board (extension > £150k)

Contact Officer (Name & number)

Matt Wall 0161 793 3993

Lead Service Group

Service Reform & Development

How the contract was procured?

(to be supplied by procurement)

Framework Call-off (Mini Competition)

Framework Details (where applicable)

(procurement body, framework reference & title, start/ end date

Crown Commercial Service (CCS) RM6068 Technology Products & Associated Services

Framework Start Date: 10.12.2019

Framework End Date: 09.12.2023

https://www.crowncommercial.gov.uk/agreements/RM6068

Funding Source

Revenue Budget

 

 

 


 

The Reasons are

To seek approval for the award of the above mentioned contract in relation to the larger [MY]Work enablement project, this aligns into the building refurbishment campus upgrade and enhances the safe return to work for SCC staff.

 

Key outcomes achieved by this Tender

·         Enhance digital agility of hybrid working within aligned to City Councils wider [MY]Work methodology

·         Meeting room improvements

·         Software/hardware integration to existing digital infrastructure

·         Statistical analysis for future strategic decisions

 

Options considered and rejected were

None

 

Assessment of Risk

 

If the Council chose not to award a contract following this procurement exercise, the Council’s return to work programme ([MY]Work) expectations that have been relayed to staff and stakeholders will not be achieved, in turn the safety guidelines also associated for safe hybrid working patterns will also not be achievable.

 

The source of funding is

Capital Budget

 

Legal Advice obtained

Yes

 

Financial Advice obtained

Yes

 

Procurement Advice obtained

Yes

 

HR Advice obtained

No

 

Climate Change Implications obtained

No

 

The following documents have been used to assist the decision process.

None

 

Contact Officer: Matt Wall

Telephone number:0161 793 3993

 

The Lead Member has been consulted and is supportive of the proposed contract.

 

The appropriate Scrutiny Committee to call-in the decision is the Overview and Scrutiny Board

 

Signed:  Councillor Bill Hinds        Dated: 14.12.21

            Lead Member for Finance & Support Services

 

 

*           This decision was published on 14.12.21

*           This decision will come in force at 4.00 p.m. on 21.12.21. unless it is called-in in accordance with the Decision Making Process Rules.

 

7.

Exclusion of the public

8.

Decision items - Part 2 (closed to the public)

9.

Date and time of next meeting

10:00am on Wednesday 12th January 2022 in the Salford Suite, Civic Centre, Chorley Road, Swinton, M27 5DA.